On March 15th 2019, China Tianying(CNTY) received the Award Notification Letter from the Urban Administration Bureau of Xiangcheng, Zhoukou City, Henan Province, confirming that it had successfully won the bid for a Waste-to-Energy(WTE) BOT project. The proposed price was around RMB445 million, with a proposed waste treatment fee at RMB68/tonne.
The WTE plant is planned to be built in Niutan Village Zhengguo Township of Xiangcheng County. The BOT project has a concession of 30 years(including 24 months of construction). The plan is to build a WTE plant with a capacity of 1200 tonnes/day. In Phase one, it will be equipped with two 400t/d mechanical grate furnaces and one 15MW steam turbine generator; in Phase two, another 400t/d mechanical grate furnace and a 7.5MW steam turbine generator will be added. The main structure will be completed during Phase one. The plant is expected to run for no less than 8000 hours a year.